Saturday 14 April 2012

Compile/get the result


Week 11

Title of the activity:  Compile/get the result

Objective:

  • To obtain this project working based on expected
  • To ensure the project is follow the main objective of this project or not

Content/Procedure:

  • Understand the main objective
  • Get the result based on objective

Objective of project

·         To develop a machine that composes of agriculture waste into    organic fertilizer through the combination of software and hardware.
·         To demonstrate the automation system of the machine that effectively transforms the waste into useful fertilizer.
·         To evaluate the functionality of the machine this can help to save the environment by recycling the organic waste for agricultural application.

Analysis

Based on project, result is taken by rotation motor and time setting. Then, lamp or heater circuit should detect the actual temperature refer to set point. For example, set point of temperature set is 35°c, if temperature detect below than this value, lamp will switch on to produce heat in drum. Also if temperature over for set point, lamp will switch off mean temperature in drum already achieve the set point temperature. Below are the classifications of heat condition
·         0%- lamp ON in turbo condition (100%)
·         50%-lamp ON (50%) and OFF (50%)
·         100%-lamp OFF (100%)

    Relation between set point and actual temperature

   Conclusion:
   As a conclusion, the main objective of this project is achieved when proved by taken the result of this project.







No comments:

Post a Comment